Back to projects

Construction of an Outdoor Recreation Court at Crossings

Ramara, Ontario

completeRecreationCCRIS
Federal contribution
$38,500
Federal share40%

of $96.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 8, 2021
2021202220232024
Built

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Township of Ramara
Construction start
Jun 13, 2024(actual)
Construction end
Aug 9, 2024(actual)

Against the original forecast

  • Construction start10 months lateforecast Aug 1, 2023
  • Construction end10 months lateforecast Sep 30, 2023

Also in Ramara