Rehabilitation of Pine Point and Bill Bolton Arenas
Federal contribution
$1.3M
$1,262,327
Federal share37%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 13, 2021
today
2021202320252027
BuiltForecast
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Toronto
- Construction start
- Apr 15, 2025(actual)
- Construction end
- Aug 31, 2028(forecast)