Refurbishment of the Glengarry Sports Palace

North Glengarry, Ontario

completeRecreationCCRIS
Federal contribution
$863,550
Federal share40%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 29, 2021
20212022
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Township of North Glengarry
Construction start
Apr 1, 2022(actual)
Construction end
Nov 10, 2022(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Dec 31, 2022

Also in North Glengarry

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57975 in the federal list. How to read these figures.