Alexandria Lagoon Upgrade Detailed Design
Federal contribution
$210,946
Federal share28%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of North Glengarry
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start6 months lateforecast Jan 2, 2017
- Construction end3 months earlyforecast Mar 31, 2020