Back to projects

Construction of a Tamil Community Centre (TCC) in Northeast Scarborough

Toronto, Ontario

approvedCultureCCRIS
Federal contribution
$14.4M
$14,399,814
Federal share40%

of $36.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 16, 2021
today
20212023202520272029
BuiltForecast

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Tamil Community Centre
Construction start
May 1, 2027(forecast)
Construction end
Aug 31, 2029(forecast)

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57997 in the federal list. How to read these figures.