Rehabilitation of a century church building and 3-storey rear addition Community Centre

Guelph, Ontario

completeCultureCCRIS
Federal contribution
$220,156
Federal share40%

of $550.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2021
20222023
Built

Approved 5 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
HOPE House
Construction start
May 3, 2021(actual)
Construction end
May 31, 2023(actual)

Against the original forecast

  • Construction end8 months lateforecast Sep 30, 2022