Re-Establishing Our Healing Journeys
Mississaugas of the New Credit First Nation, Ontario
Federal contribution
$3.6M
$3,556,553
Federal share66%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202120222023
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Native Horizons Treatment Center
- Construction start
- Oct 3, 2021(actual)
- Construction end
- Mar 13, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 1, 2021
- Construction end3 weeks earlyforecast Mar 31, 2023
Also in Mississaugas of the New Credit First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58016 in the federal list. How to read these figures.