Design and Contract Documents for the Completion of the Waterline
Mississaugas of the New Credit First Nation, Ontario
Federal contribution
$91,356
Federal share50%
of $182.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 10, 2017
ApprovedFeb 28, 2018
2018201920202021
Built
Approved 5 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Mississaugas of the Credit
- Construction start
- Apr 30, 2018(actual)
- Construction end
- Aug 31, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 4, 2018
- Construction end5 months lateforecast Mar 31, 2021
Also in Mississaugas of the New Credit First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51390 in the federal list. How to read these figures.