Design and Contract Documents for the Completion of the Waterline

Mississaugas of the New Credit First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$91,356
Federal share50%

of $182.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 10, 2017
ApprovedFeb 28, 2018
2018201920202021
Built

Approved 5 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Mississaugas of the Credit
Construction start
Apr 30, 2018(actual)
Construction end
Aug 31, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 4, 2018
  • Construction end5 months lateforecast Mar 31, 2021

Also in Mississaugas of the New Credit First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51390 in the federal list. How to read these figures.