Construction of a multifunctional aquatic pool outside Jack Eyamie Park
Federal contribution
$828,136
Federal share32%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 15, 2021
202120222023
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Gatineau
- Construction start
- Aug 10, 2021(actual)
- Construction end
- Jun 23, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2021
- Construction end12 months lateforecast Jun 30, 2022
Also in Gatineau
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58079 in the federal list. How to read these figures.