Upgrade of the Arthabaska community center
Federal contribution
$1.0M
$1,033,063
Federal share33%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 28, 2021
202120222023202420252026
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Victoriaville
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Oct 29, 2025(actual)
Against the original forecast
- Construction end13 months lateforecast Oct 9, 2024
Also in Victoriaville
- Protection and securing of the drinking water supply in the Beaudet Reservoir of the City of Victoriaville.$16.0M
- Victoriaville Performing Arts Centre$8.0M
- Upgrade of equipment of treatment of wastewater in the STEP$2.4M
- Replacement of ventilation systems serving the medical imaging sector (radiology and nuclear medicine)$1.4M
- Library heating and cooling systems (Phases 2 and 3)$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58091 in the federal list. How to read these figures.