Upgrade of equipment of treatment of wastewater in the STEP

Victoriaville, Quebec

completeWastewaterCWWF
Federal contribution
$2.4M
$2,441,266
Federal share48%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
20172018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Victoriaville
Construction start
Oct 2, 2017(actual)
Construction end
Aug 13, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 17, 2017
  • Construction end8 months earlyforecast Mar 31, 2019