Upgrade of equipment of treatment of wastewater in the STEP
Federal contribution
$2.4M
$2,441,266
Federal share48%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
20172018
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Victoriaville
- Construction start
- Oct 2, 2017(actual)
- Construction end
- Aug 13, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 17, 2017
- Construction end8 months earlyforecast Mar 31, 2019
Also in Victoriaville
- Protection and securing of the drinking water supply in the Beaudet Reservoir of the City of Victoriaville.$16.0M
- Victoriaville Performing Arts Centre$8.0M
- Replacement of ventilation systems serving the medical imaging sector (radiology and nuclear medicine)$1.4M
- Upgrade of the Arthabaska community center$1.0M
- Library heating and cooling systems (Phases 2 and 3)$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48830 in the federal list. How to read these figures.