College of the North Atlantic (Port aux Basques Campus) Roof Replacement

Channel-Port aux Basques, Newfoundland and Labrador

completeEducation, Training and ChildcareCVRIS
Federal contribution
$256,000
Federal share80%

of $320.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 17, 2020
20212022
Built

Approved 2 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 20, 2022(actual)
Construction end
Aug 22, 2022(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Jul 26, 2022