Downtown Civic Square Revitization
Federal contribution
$2.0M
$1,984,900
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 9, 2021
today
2021202320252027
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Burlington
- Construction start
- Apr 21, 2026(actual)
- Construction end
- Nov 30, 2026(forecast)
Against the original forecast
- Construction start7 weeks lateforecast Mar 2, 2026
Also in Burlington
- Halton Region Wastewater Treatment (Skyway Facility)$51.4M
- Replacement of Access Points; Open Concept Schools; Building Automation Systems & Controls Upgrade; Child Care Retrofits & Outdoor Spaces$6.9M
- Portable Classroom Ventilation Improvements; HVAC Improvements; Window Replacement$5.6M
- Improvements to HVAC, Windows, Bottle Filling Stations, Washrooms, Doors, Child Care Centre, WiFi and Network Infrastructure$5.4M
- Highway 403 - Rehabilitation and Resurfacing$4.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58190 in the federal list. How to read these figures.