Foundation Waterproofing and Mould Remediation
Federal contribution
$594,071
Federal share40%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2021
today
2021202320252027
BuiltForecast
Approved 7 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Parkdale Activity Recreation Centre
- Construction start
- Nov 4, 2021(actual)
- Construction end
- Mar 31, 2027(forecast)