Back to projects

Foundation Waterproofing and Mould Remediation

Toronto, Ontario

underwayRecreationCCRIS
Federal contribution
$594,071
Federal share40%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2021
today
2021202320252027
BuiltForecast

Approved 7 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Nov 4, 2021(actual)
Construction end
Mar 31, 2027(forecast)

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58215 in the federal list. How to read these figures.