Building 909 Roof Replacement

St. John's, Newfoundland and Labrador

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$200,376
Federal share80%

of $250.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
20212022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 27, 2022(actual)
Construction end
Aug 22, 2022(actual)

Against the original forecast

  • Construction start6 months lateforecast Nov 8, 2021
  • Construction end8 weeks lateforecast Jun 30, 2022

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58276 in the federal list. How to read these figures.