College of the North Atlantic (Carbonear Campus) HVAC Controls Upgrade

Carbonear, Newfoundland and Labrador

completeVentilationCVRIS
Federal contribution
$81,936
Federal share80%

of $102.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 12, 2021
2021
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 24, 2021(actual)
Construction end
Mar 31, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Dec 23, 2020
  • Construction end3 months earlyforecast Jun 30, 2021