College of the North Atlantic (Carbonear Campus) HVAC Controls Upgrade
Carbonear, Newfoundland and Labrador
Federal contribution
$81,936
Federal share80%
of $102.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 12, 2021
2021
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Construction start
- Feb 24, 2021(actual)
- Construction end
- Mar 31, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast Dec 23, 2020
- Construction end3 months earlyforecast Jun 30, 2021
Also in Carbonear
- Upgrades to Route 70- Interchange at Valley Road and Route 75 - Veterans Memorial Highway$2.2M
- Water System Upgrading$807.0K
- Adelaide Street Water Sewer Storm Street Upgrades Ph2$587.6K
- Water Street Water, Sewer and Street Upgrading$517.8K
- Water Street - Water, Sewer and Street Upgrading Phase 3$473.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58278 in the federal list. How to read these figures.