Back to projects

Supreme Court Accessibility Upgrades

St. John's, Newfoundland and Labrador

completeOtherCVRIS
Federal contribution
$314,162
Federal share80%

of $392.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2021202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 13, 2023(actual)
Construction end
Dec 20, 2023(actual)

Against the original forecast

  • Construction end7 weeks lateforecast Oct 30, 2023