Building 904 Boiler Plant - Boiler Blow Down Tank Replacement
St. John's, Newfoundland and Labrador
Federal contribution
$16,000
Federal share80%
of $20.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Construction start
- Jan 19, 2021(actual)
- Construction end
- Mar 31, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Dec 23, 2020
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58295 in the federal list. How to read these figures.