Stephenville Correctional Center Flooring Upgrades

Stephenville, Newfoundland and Labrador

completeOtherCVRIS
Federal contribution
$21,670
Federal share80%

of $27.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 2, 2021(actual)
Construction end
Mar 31, 2021(actual)