Stephenville Arts and Culture Center Theatre Lighting Upgrade

Stephenville, Newfoundland and Labrador

completeCultureCVRIS
Federal contribution
$68,000
Federal share80%

of $85.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
20212022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 15, 2022(actual)
Construction end
Mar 11, 2022(actual)

Against the original forecast

  • Construction start6 months lateforecast Aug 3, 2021
  • Construction end3 months earlyforecast May 31, 2022