Stephenville Arts and Culture Center Theatre Lighting Upgrade
Stephenville, Newfoundland and Labrador
Federal contribution
$68,000
Federal share80%
of $85.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
20212022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Construction start
- Feb 15, 2022(actual)
- Construction end
- Mar 11, 2022(actual)
Against the original forecast
- Construction start6 months lateforecast Aug 3, 2021
- Construction end3 months earlyforecast May 31, 2022
Also in Stephenville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58305 in the federal list. How to read these figures.