Boil Water Advisory Remediation
St. Joseph's, Newfoundland and Labrador
Federal contribution
$42,121
Federal share40%
of $105.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 18, 2021
20212022202320242025
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- St. Joseph's
- Construction start
- Oct 22, 2024(actual)
- Construction end
- Nov 15, 2024(actual)
Against the original forecast
- Construction start9 months lateforecast Jan 18, 2024
- Construction end9 months lateforecast Feb 19, 2024
Also in St. Joseph's