Lower Road Rehabilitation
St. Joseph's, Newfoundland and Labrador
Federal contribution
$40,773
Federal share33%
of $122.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2024
2024
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- St. Joseph's
- Construction start
- May 28, 2024(actual)
- Construction end
- Aug 14, 2024(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 3, 2024
- Construction end2 weeks lateforecast Jul 31, 2024