Crouchers Brook Boil Water Advisory

Glenburnie-Birchy Head-Shoal Brook, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$64,893
Federal share38%

of $169.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2021
202120222023
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 12, 2022(actual)
Construction end
Sep 12, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2022
  • Construction end3 months earlyforecast Nov 30, 2023

Also in Glenburnie-Birchy Head-Shoal Brook

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58340 in the federal list. How to read these figures.