Crouchers Brook Boil Water Advisory
Glenburnie-Birchy Head-Shoal Brook, Newfoundland and Labrador
Federal contribution
$64,893
Federal share38%
of $169.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 18, 2021
202120222023
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Glenburnie-Birchy Head-Shoal Brook
- Construction start
- Sep 12, 2022(actual)
- Construction end
- Sep 12, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2022
- Construction end3 months earlyforecast Nov 30, 2023
Also in Glenburnie-Birchy Head-Shoal Brook
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58340 in the federal list. How to read these figures.