Crouchers Brook Water System
Glenburnie-Birchy Head-Shoal Brook, Newfoundland and Labrador
Federal contribution
$257,541
Federal share50%
of $515.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Glenburnie-Birchy Head-Shoal Brook
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Sep 28, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 31, 2017
- Construction end3 months earlyforecast Dec 31, 2018