Paving of Oak River Roads

Oakview, Manitoba

completeHighways and RoadsRNIS
Federal contribution
$240,000
Federal share60%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2021
Built

Approved 6 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Aug 15, 2021(actual)
Construction end
Aug 31, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2021
  • Construction end2 months earlyforecast Oct 31, 2021

Also in Oakview

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58366 in the federal list. How to read these figures.