Paving of Oak River Roads
Federal contribution
$240,000
Federal share60%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2021
Built
Approved 6 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Oakview
- Construction start
- Aug 15, 2021(actual)
- Construction end
- Aug 31, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2021
- Construction end2 months earlyforecast Oct 31, 2021
Also in Oakview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58366 in the federal list. How to read these figures.