Rapid City Water Distribution System
Federal contribution
$2.6M
$2,611,042
Federal share40%
of $6.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2022
2023202420252026
BuiltForecast
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Oakview
- Construction start
- May 13, 2024(actual)
- Construction end
- Jul 31, 2026(forecast)
Against the original forecast
- Construction start6 weeks lateforecast Apr 1, 2024
Also in Oakview
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62687 in the federal list. How to read these figures.