2020 Water Transmission Main Phase II
Woodstock, Newfoundland and Labrador
Federal contribution
$28,461
Federal share40%
of $71.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Woodstock
- Construction start
- Jul 15, 2022(actual)
- Construction end
- Jan 20, 2023(actual)
Against the original forecast
- Construction end7 months earlyforecast Aug 31, 2023
Also in Woodstock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58422 in the federal list. How to read these figures.