2020 Water Transmission Main Phase II

Woodstock, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$28,461
Federal share40%

of $71.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Woodstock
Construction start
Jul 15, 2022(actual)
Construction end
Jan 20, 2023(actual)

Against the original forecast

  • Construction end7 months earlyforecast Aug 31, 2023