Water Transmission Main
Woodstock, Newfoundland and Labrador
Federal contribution
$310,454
Federal share50%
of $621.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Woodstock
- Construction start
- Oct 16, 2017(actual)
- Construction end
- Dec 10, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 1, 2017
- Construction end4 months lateforecast Aug 20, 2017
Also in Woodstock