Back to projects

Water Transmission Main

Woodstock, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$310,454
Federal share50%

of $621.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Woodstock
Construction start
Oct 16, 2017(actual)
Construction end
Dec 10, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 1, 2017
  • Construction end4 months lateforecast Aug 20, 2017

Also in Woodstock

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46959 in the federal list. How to read these figures.