Arena Roof - Moncton
Federal contribution
$213,484
Federal share71%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Moncton
- Construction start
- Sep 27, 2021(actual)
- Construction end
- Dec 24, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 16, 2021
- Construction end3 weeks lateforecast Nov 30, 2021
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58427 in the federal list. How to read these figures.