Various Sidewalk Repair - Moncton
Federal contribution
$550,608
Federal share80%
of $688.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 9, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Moncton
- Construction start
- Jun 21, 2021(actual)
- Construction end
- Jul 29, 2022(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jul 19, 2021
- Construction end2 weeks lateforecast Jul 15, 2022
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58436 in the federal list. How to read these figures.