Lewisville Park - Moncton
Federal contribution
$520,000
Federal share74%
of $699.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Moncton
- Construction start
- Jun 16, 2021(actual)
- Construction end
- Sep 29, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 24, 2021
- Construction end8 months earlyforecast May 31, 2023
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58438 in the federal list. How to read these figures.