Back to projects

Mapleton Park: Bayou Trail Bridge Replacement

Moncton, New Brunswick

completeActive TransportationCVRIS
Federal contribution
$99,426
Federal share66%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Moncton
Construction start
Jul 15, 2021(actual)
Construction end
Nov 5, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2021
  • Construction end3 months lateforecast Aug 13, 2021

Also in Moncton