Irishtown Nature Park Trail Upgrades - Moncton
Federal contribution
$143,729
Federal share80%
of $179.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Moncton
- Construction start
- Aug 16, 2021(actual)
- Construction end
- Jun 13, 2022(actual)
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M