Back to projects

Whitehorse Transit Services: Bus Midlife Refurbishments 2021 - 2023

Whitehorse, Yukon

completePublic TransitPTIS
Federal contribution
$416,973
Federal share75%

of $556.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2021
20222023
Built

Approved 6 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Whitehorse
Construction start
Jul 1, 2021(actual)
Construction end
May 31, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2021
  • Construction end7 months earlyforecast Dec 31, 2023

Also in Whitehorse

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58472 in the federal list. How to read these figures.