Whitehorse Transit Services: Bus Midlife Refurbishments 2021 - 2023
Federal contribution
$416,973
Federal share75%
of $556.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2021
20222023
Built
Approved 6 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Whitehorse
- Construction start
- Jul 1, 2021(actual)
- Construction end
- May 31, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2021
- Construction end7 months earlyforecast Dec 31, 2023
Also in Whitehorse
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58472 in the federal list. How to read these figures.