Strathcona County New Trail Connections for Active Living

Strathcona County, Alberta

completeActive TransportationCVRIS
Federal contribution
$982,165
Federal share80%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
202220232024
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
County of Strathcona
Construction start
May 1, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start12 months earlyforecast May 1, 2022
  • Construction end12 months earlyforecast Dec 31, 2024