Airdrie Canadian Pacific Railway Luxstone Pedestrian Tunnel Construction
Federal contribution
$1.2M
$1,200,000
Federal share80%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
20222023
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Airdrie
- Construction start
- May 1, 2021(actual)
- Construction end
- Mar 10, 2023(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 1, 2021
- Construction end3 weeks earlyforecast Mar 31, 2023
Also in Airdrie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58494 in the federal list. How to read these figures.