Airdrie Lifecycle Parks Pathways
Federal contribution
$131,941
Federal share80%
of $164.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Airdrie
- Construction start
- Jul 29, 2021(actual)
- Construction end
- Aug 31, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 30, 2021
- Construction end7 months earlyforecast Mar 31, 2022
Also in Airdrie
- City of Airdrie - 40th Avenue Phase 1 and 2$3.0M
- Veterans Boulevard Upgrade - 8th Street to 24th Street$2.1M
- Airdrie Canadian Pacific Railway Luxstone Pedestrian Tunnel Construction$1.2M
- Airdrie Genesis Place Pool Mechanical & Field House Board System Replacement$467.3K
- Airdrie Plainsmen Arena North Drainage and Siding$215.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58496 in the federal list. How to read these figures.