Optimizing Air Quality in Schools

North Bay, Ontario

completeVentilationCVRIS
Federal contribution
$3.2M
$3,194,167
Federal share80%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jan 6, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Sep 1, 2021