Optimize air quality
Federal contribution
$448,000
Federal share80%
of $560.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
20212022202320242025
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Conseil Scolaire de District Catholique du Nouvel-Ontario
- Construction start
- Apr 1, 2022(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start5 months earlyforecast Sep 1, 2022
- Construction end12 months lateforecast Dec 31, 2023
Also in Greater Sudbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58563 in the federal list. How to read these figures.