Back to projects

Hybrid Learning Classroom Implementation Project - WiFi Access Points

Toronto, Ontario

completeEducation, Training and ChildcareCVRIS
Federal contribution
$7.6M
$7,596,261
Federal share80%

of $9.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 25, 2021(actual)
Construction end
Oct 30, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Feb 18, 2021
  • Construction end2 months earlyforecast Dec 31, 2023

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58621 in the federal list. How to read these figures.