Wireless Infrastructure Upgrade Project Group
Federal contribution
$2.6M
$2,565,806
Federal share80%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Durham District School Board
- Construction start
- May 12, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Feb 18, 2021
Also in Whitby
- Whitby Sports Complex$25.0M
- Ventilation Upgrade; Window Replacements; Exterior Door FOB Access; Water Bottle Filling and Hand Sanitizing Station; Childcare Vestibules; Plexiglass Partitions; Fencing$7.6M
- Outdoor Classrooms Replacement of Portable Classrooms$3.8M
- Waterfront Trail Redevelopment for Whitby, Ontario$2.6M
- Whitby Civic Centre Recreation Complex Rehabilitation and Renovations$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58653 in the federal list. How to read these figures.