Waterfront Trail Redevelopment for Whitby, Ontario
Federal contribution
$2.6M
$2,599,377
Federal share41%
of $6.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 11, 2023
202320242025
Built
Approved 10 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Whitby
- Construction start
- Jul 19, 2024(actual)
- Construction end
- Oct 1, 2025(actual)
Against the original forecast
- Construction start10 months lateforecast Oct 2, 2023
- Construction end4 months earlyforecast Jan 31, 2026
Also in Whitby
- Whitby Sports Complex$25.0M
- Ventilation Upgrade; Window Replacements; Exterior Door FOB Access; Water Bottle Filling and Hand Sanitizing Station; Childcare Vestibules; Plexiglass Partitions; Fencing$7.6M
- Outdoor Classrooms Replacement of Portable Classrooms$3.8M
- Wireless Infrastructure Upgrade Project Group$2.6M
- Whitby Civic Centre Recreation Complex Rehabilitation and Renovations$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64298 in the federal list. How to read these figures.