Waterfront Trail Redevelopment for Whitby, Ontario

Whitby, Ontario

completeActive TransportationATF
Federal contribution
$2.6M
$2,599,377
Federal share41%

of $6.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 11, 2023
202320242025
Built

Approved 10 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Whitby
Construction start
Jul 19, 2024(actual)
Construction end
Oct 1, 2025(actual)

Against the original forecast

  • Construction start10 months lateforecast Oct 2, 2023
  • Construction end4 months earlyforecast Jan 31, 2026

Also in Whitby