HVAC Upgrades and Hands Free Bottle Filling at Various Locations
Federal contribution
$600,000
Federal share80%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
2022
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Kawartha Pine Ridge District School Board
- Construction start
- Jul 1, 2021(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 18, 2021
- Construction end12 months earlyforecast Dec 31, 2022
Also in Peterborough
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58671 in the federal list. How to read these figures.