Ventilation Upgrade; Bottle filling station; Handwashing Station
Federal contribution
$1.7M
$1,686,000
Federal share80%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Rainbow District School Board
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Feb 18, 2021
Also in Greater Sudbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58683 in the federal list. How to read these figures.