HVAC Upgrades

Greater Sudbury, Ontario

completeVentilationCVRIS
Federal contribution
$1.2M
$1,227,094
Federal share79%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 18, 2021
  • Construction end4 months earlyforecast Dec 31, 2023

Also in Greater Sudbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58685 in the federal list. How to read these figures.