HVAC Replacements and Portable Ventilation Upgrades; Window replacement

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$3.8M
$3,847,668
Federal share80%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 1, 2021(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Feb 18, 2021
  • Construction end4 months earlyforecast Dec 31, 2023