Handwashing Upgrades and Bottle Fill Station Installation

Greater Sudbury, Ontario

completeEducation, Training and ChildcareCVRIS
Federal contribution
$75,200
Federal share80%

of $94.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Nov 30, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 18, 2021
  • Construction end4 months earlyforecast Mar 31, 2022