Windows; HVAC

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$1.7M
$1,664,000
Federal share80%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Conseil Scolaire Viamonde
Construction start
Apr 1, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Feb 18, 2021