Window Replacement
Federal contribution
$2.2M
$2,236,020
Federal share80%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
20222023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Rainbow District School Board
- Construction start
- Mar 26, 2021(actual)
- Construction end
- Aug 31, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast Feb 18, 2021
- Construction end4 months earlyforecast Dec 31, 2023
Also in Greater Sudbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58702 in the federal list. How to read these figures.