HVAC upgrades; Installation of touchless Handwashing sinks; Portable Replacements; WiFi Access points and network infrastructure; Water bottle filling stations; Window Replacement
Federal contribution
$6.6M
$6,596,442
Federal share80%
of $8.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Construction start
- Feb 24, 2021(actual)
- Construction end
- Dec 31, 2023(actual)