HVAC upgrades; Installation of touchless Handwashing sinks; Portable Replacements; WiFi Access points and network infrastructure; Water bottle filling stations; Window Replacement

Peterborough, Ontario

completeVentilationCVRIS
Federal contribution
$6.6M
$6,596,442
Federal share80%

of $8.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 24, 2021(actual)
Construction end
Dec 31, 2023(actual)

Also in Peterborough

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58712 in the federal list. How to read these figures.